ALDOT is aligning Lakeshore Parkway with Morgan Road at SR-150.
Work to tie Lakeshore Parkway with Morgan Road at SR-150 should be complete by the end of 2027.
Apr 21, 2026

Work to transform a major west Jefferson County intersection is experiencing significant progress.

The Alabama Department of Transportation (ALDOT) is working to tie Morgan Road directly in with Lakeshore Parkway. The project is a partnership with the City of Bessemer and Jefferson County.

The future connection at SR-150 grows more visible by the day since work began in December. 

This aerial view clearly shows the future Morgan Road connection at SR-150.

Crews continue carving out the future intersection path near the Starlight Baptist Church.

The project should improve traffic flow in an area home to a growing number of industrial campuses.  That group of nearby distribution centers includes Lowe’s, Carvana, Dollar General and FedEx Ground.  

The alignment will help connect Morgan Road travelers to the upcoming Diverging Diamond Interchange on Lakeshore Parkway at I-65 in Homewood.  Jefferson County’s second DDI should open to traffic by the end of 2027.

The future Lakeshore Parkway Diverging Diamond Interchange at I-65 should be open by the end of 2027.

In addition, the work will widen SR-150 between Morgan and Shannon Roads from three to five lanes.

Right now, that stretch of roadway averages nearly 20,000 vehicles a day.

In the heart of widening SR-150, ALDOT will replace the 93-year-old bridge over Little Shades Creek. 

Work is progressing on the new bridge over Little Shades Creek on SR-150.

The 58-foot span is located just east of Lakeshore Parkway. Its replacement could be complete by the end of 2026.

The work to align Morgan Road with Lakeshore Parkway should take an additional year. 

Related Project
New alignment of Morgan Road and Lakeshore Parkway at SR-150 in Bessemer.
Region/County East Central/Jefferson
Type of WorkConstructing the relocation and intersection improvements (grading, drainage, pavement, and traffic signals) on Lakeshore Parkway and Morgan Road from the junction of Cumberland Road to a point 1000 feet north of Turin Drive to include the widening (grading, drainage, and pavement) on SR-150 from the junction of CR-52 (Morgan Road) to the junction of Lakeshore Parkway in Bessemer.
RouteSR-150 at CR-52 and SR-149 in Bessemer
Projected StartDecember 2025
Projected CompletionEnd of 2027