This project is resurfacing about seven miles of US-431 from the Etowah County line to SR-75 in Albertville. All mainline through-lane paving is complete, and the contractor is currently paving crossovers, turn lanes, and intersection and driveway tie-ins.
Region/County | North/Marshall |
Type of Work | Resurfacing |
Route | US-431 |
Projected Start | August 2023 |
Projected Completion | Spring 2024 |
Traffic Impact | Daytime and nighttime single-lane closures |
Project Number | NH-0001(630) |
Project Cost | $6,514,010.00 |
Project Status | Completed |