The Alabama Department of Transportation (ALDOT) plans to resurface and install guardrail on US-82 from Wilson Road to SR-5 in Brent to improve mobility and safety.
The 3.65-mile project is scheduled to begin Wednesday, Aug. 13 and will continue until early 2026, weather permitting. At least one lane will be open in each direction throughout the duration of the project.
Wiregrass Construction Company was awarded the project at $2.92 million.
Motorists should expect possible delays and are encouraged to observe work-zone speed limits.
For real-time traffic updates and more, download the ALGOTraffic app or visit ALGOTraffic.com.
| Region/County | West Central/Bibb |
| Type of Work | Resurfacing |
| Route | US-82 |
| Projected Start | August 13, 2025 |
| Projected Completion | Early 2026 |
| Project Number | NH-HSIP-FMGR-0006(605) |
| Project Cost | $2,920,000.00 |
| Project Status | Substantially Complete |