| Region/County | East Central/Talladega |
| Type of Work | For constructing the micro-fine milling, resurfacing, guardrail installation, and traffic stripe on I-20 from a point beginning at the 6-lane section (MP 173.218) to the H.J. Bentley Jr. Parkway overpass (MP 181.700) west of Oxford. Length 8.481 mi. |
| Route | I-20 |
| Projected Start | Spring 2026 |
| Projected Completion | Spring 2027 |
| Project Number | IM-IMGR-I020(370) |
| Project Cost | $6,434,033 |
| Project Status | Upcoming |
I-20 resurfacing between Talladega and Oxford
Get the latest traffic information at algotraffic.com or on the ALGO Traffic app.
Related Posts
ALDOT has kicked of an eight-mile resurfacing project on I-20 in Talladega.
Sunday night, the Alabama Department of Transportation kicked off nightly lane closures to start resurfacing eight miles of I-20 in Talladega.
The work stretches from the Eastaboga Interchange to the H.J. Bentley Jr. Parkway Overpass.
The contractor will mill off the old asphalt, re-surface, install guardrails and apply traffic striping. Ramp and Interchange work at…