The Alabama Department of Transportation (ALDOT) plans to resurface SR-13 from the intersection of SR-18 to the intersection of SR-102 northwest of Berry in Fayette County to improve mobility and safety.
The 11.5-mile project is expected to begin Monday, April 13, and will continue until late fall 2026, weather permitting. A pilot car will guide traffic through the work zone.
Drivers should expect possible delays and are encouraged to observe work-zone speed limits.
S.T. Bunn Construction Company was awarded the project at $3.42 million.
For real-time traffic updates and more, download the ALGOTraffic app or visit ALGOTraffic.com. For information about this project and others, visit ALDOTNews.com.
| Region/County | West Central/Fayette |
| Type of Work | Resurfacing |
| Route | SR-13 |
| Projected Start | April 13, 2026 |
| Projected Completion | Late fall 2026 |
| Project Number | NH-FMGR-0013(645) |
| Project Cost | $3,424,497.00 |
| Project Status | Active |