The $5 million project will improve operations at several intersections on SR-35, including the junctions with the southbound I-59 on- and off-ramps and Airport Road/Jordan Road, seen here looking west from near the interstate.

Work to improve operations at several intersections on SR-35 in Fort Payne will begin this week.

The nearly $5 million project with contractor Wiregrass Construction extends about 1.7 miles from Dewyer Avenue to Prestwood Drive.

Intersection improvements

The project will make improvements to the SR-35 intersections with Jordan Road/Airport Road, the I-59 interchange ramps…

Read More “SR-35 intersection improvements in Fort Payne to begin”

Previous stakeholder meetings and surveys helped identify several preliminary alternative alignments for SR-35.

ALDOT will hold in-person and online public involvement meetings to gather input on potential improvements to SR-35 in Fort Payne.

The feedback will become part of a planning and environmental linkage (PEL) study. ALDOT initiated the PEL study after the City of Fort Payne received funding through a federal grant.

In-person meeting

ALDOT will…

Read More “ALDOT seeks input for Fort Payne PEL study”

ALDOT's contractor will perform an emergency slab repair and replacement on I-59 between Fort Payne and Collinsville. The effects of the underlying concrete slabs deteriorating can be seen northbound near Portersville Gap Road.

An emergency slab repair and replacement project on 13 miles of I-59 in DeKalb County will begin Monday, July 14.

Contractor Vulcan Materials will repair and replace some of the underlying concrete slabs on I-59 northbound and southbound between Exit 205 at SR-68 in Collinsville and Exit 218 at SR-35 in Fort Payne. In addition,…

Read More “I-59 emergency slab repair to begin July 14”

ALDOT opened bids Friday, June 27, for a project to improve operations on SR-35 near I-59 in Fort Payne.

Of three bidders, contractor Wiregrass Construction submitted the apparent low bid of $4,997,900.

Project details

The project features improvements to increase the functionality of the SR-35 intersections with Jordan Road/Airport Road, the I-59 interchange ramps at Exit 218,…

Read More “ALDOT lets project to improve operations on SR-35 in Fort Payne”

During lane closures, northbound US-11/Gault Avenue through traffic will be detoured to First Street to Godfrey Avenue then to Fifth Street NE in Fort Payne.

A sidewalk improvement project on US-11/Gault Avenue in Fort Payne will start Monday, weather permitting.  

The Transportation Alternatives Program (TAP) project will install Americans with Disabilities Act-compliant sidewalks and curb ramps from First Street to Third Street North. The project also includes drainage work and curb and gutter replacement.

Through the end of the…

Read More “Fort Payne sidewalk project to start Monday”