Expected lane closures on SR-69 in Jasper for ongoing bridge replacement project

Map of the scope of work for the Jasper bridge project
Bridge replacement and intersection improvements on SR-5 over SR-69
Mar 26

Weather permitting, a portion of SR-69 in Jasper will be closed in both directions beginning at 6 a.m. on Monday, April 1, through midnight on Friday, April 5. The closure will be limited to the area near SR-5. The closure will allow contractors to place girders for a new bridge and perform other necessary work on SR-5 that travels over SR-69.

Entrance and exit ramps will remain open throughout the closure. Motorists should expect delays and are encouraged to plan alternate routes.

This work is part of the bridge replacement and intersection improvement project that is intended to improve safety, quality of life and economic development for our state. The project is expected to be completed by the end of the year.

Wright Brothers Construction Company was awarded the project at $8.8 million.

Motorists can visit ALGOtraffic.com or download the ALGO Traffic app for real-time traffic and road condition information and to subscribe to personalized traveler alerts.

Related Project
Region/County West Central/Walker
Type of WorkBridge Replacement
RouteSR-5, SR-195, SR-69, US-78A
Projected StartJanuary 17, 2024
Projected CompletionSpring 2025
Traffic ImpactBridge closure

The Alabama Department of Transportation plans to replace the bridge and make intersection improvements on SR-5 over the SR-69 underpass in Jasper.

The project is expected to begin Wednesday, January 17 with the bridge demolition, which will occur for about two weeks. Construction will then take place for approximately one year, weather permitting. The intersection…

Read More “ALDOT to replace bridge in Jasper”