Skip to content
ALDOT News Hub

Reconstruction of I-59S near state line ahead

Traffic drives past a large green "Welcome to Sweet Home Alabama" sign. Orange and white drums line the roadway.
The project to reconstruct and rehabilitate the southbound I-59 roadway extends from the state line nearly to Fort Payne.
May 21, 2026

Alabama Welcome Center to close for first phase of work

A $47.5 million project for reconstruction and rehabilitation of 16 miles of I-59 southbound near the Georgia state line will begin after Memorial Day.

From the state line to about a mile north of the US-11 overpass in Fort Payne, contractor Wiregrass Construction will demolish and replace about 10 miles of the roadway and rehabilitate another six miles.

Welcome center to close

The first phase of the project will tackle a roughly one-mile stretch of I-59 southbound from the state line to south of the Alabama Welcome Center on I-59 in DeKalb County.

Beginning Tuesday, May 26, weather permitting, Wiregrass expects to begin milling and paving the inside southbound lane and shoulder in that area. ALDOT advises motorists to expect single-lane closures. For real-time traffic and road condition information, visit ALGOtraffic.com or download the ALGO Traffic app.

Next, the contractor will install concrete barriers to close the outside southbound lane and begin work to demolish and reconstruct the outside lane. The lane closure will necessitate a 90-day closure of the welcome center beginning Monday, June 1.

Bushes with flowers line a path to a building.
The Alabama Welcome Center on I-59 in DeKalb County will temporarily close during the first phase of the I-59 southbound reconstruction project. Many travelers love the welcome center for its rustic feel and friendly, helpful staff.

Once the outside lane is reconstructed, the contractor will swap traffic to the new outside lane and the welcome center will reopen. Wiregrass will then reconstruct the inside lane in a similar fashion.

An aerial view of I-59,  juxtaposes a new roadway on one side and an old one on the other
This aerial view shows, at right, a recently-reconstructed segment of the northbound roadway, and left, part of the southbound roadway to be reconstructed in this project.

Later phases

Two later phases will each shut down roughly five-mile segments of the southbound roadway for extended periods while Wiregrass demolishes and reconstructs the roadway. During these phases, all traffic will shift to the northbound roadway, with northbound and southbound traffic separated by barriers.

Those phases will be similar to the phasing of earlier I-59 reconstruction projects. During those projects, contractors replaced eight- to ten-mile segments of either the northbound or southbound roadway by closing and reconstructing four or five miles at a time in separate phases within each project.

This project will address a longer segment overall and includes several miles of roadway that will undergo extensive repairs rather than full reconstruction.

ALDOT anticipates completion in February 2029.

Workers paving a new roadway with a paving machine
In addition to the southbound I-59 reconstruction project that is about to begin, the contractor, Wiregrass Construction, is currently working north of Hammondville on the last major phase of an eight-mile project to replace the northbound roadway near the state line.

I-59 reconstruction

The project is the sixth in an ongoing effort to reconstruct I-59 in northeast Alabama. Two other reconstruction projects remain currently active on I-59 in DeKalb County, northbound near the state line and southbound going into Etowah County.

Since 2020, ALDOT has awarded $239.2 million in contracts to reconstruct I-59. When this project is complete, nearly two-thirds of I-59 from south of Stephens Gap Road north of Gadsden in Etowah County to the state line will have been reconstructed. Many additional miles will have undergone widening and rehabilitation as part of these projects.

A roller rolls over a road in profile, showing the build-up of the roadway.
All drivers see on completed segments of I-59 is the surface of the asphalt, but reconstruction goes much deeper — improving the subgrade and constructing a new crushed aggregate base before paving multiple layers of asphalt on top.

ALDOT anticipates letting later this year a seventh project, which will reconstruct the northbound roadway, from north of SR-68 at Collinsville to Exit 218 at SR-35 in Fort Payne.

The effort is a costly but much-needed investment in the infrastructure supporting northeast Alabama. Age and deterioration of the underlying concrete roadways necessitated total reconstruction for much of the highway.

A roadway with an excavator parked next to it. In the median is a large pile of broken concrete slabs.
A multitude of broken concrete slabs removed during I-59 reconstruction piled in the median next to a recently-paved segment of the northbound roadway.

Ongoing I-59 reconstruction projects

Wiregrass Construction continues work on the southernmost four miles of an eight-mile project to replace the northbound roadway from north of Hammondville to the state line. ALDOT anticipates completion of the $41 million project near the end of the year.

Workers level asphalt placed by a skid steer at the the edge of a road at the end of an overpass.
Vulcan Materials paves I-59 southbound at the Stephens Gap Road overpass in Etowah County, near the south end of the project, in December.

Meanwhile, contractor Vulcan Materials nears the halfway point of a $40.7 million project to reconstruct more than 10 miles of the southbound roadway in Dekalb and Etowah counties between Collinsville and Reece City, with completion planned for 2027.

Previous I-59 reconstruction projects

ALDOT previously completed three reconstruction projects on the corridor:

  • In 2022, Wiregrass finished replacing eight miles of the northbound roadway through Fort Payne at a cost of $25.2 million.
  • In 2024, Wiregrass completed reconstruction of more than 10 miles northbound between Reece City and Collinsville at a cost of $44 million.
  • In 2025, contractor A.G. Peltz Group completed the replacement of an eight-mile segment between Fort Payne and Hammondville at a cost of $40.8 million.

This southbound project starting next week parallels two of the northbound projects — the ongoing project with Wiregrass Construction and the project A.G. Peltz completed last year.

Related Project
An aerial view looking north at an interstate highway. The northbound road to the right has recently been reconstructed. The southbound road to the left is carrying two-way traffic diverted from the northbound road. An on-ramp merges to the southbound roadway. from a welcome center that is covered by the trees.
Region/County
Type of WorkReconstruction/Rehabilitation/Asphalt Pavement
RouteI-59
Projected StartSpring 2026
Projected CompletionWinter/Spring 2029
Traffic ImpactSingle-lane closures with temporary welcome center closure, and roadway closures with two-way traffic separated by barriers on opposing roadway

This project will reconstruct and rehabilitate 16 miles of I-59 southbound, from the Georgia state line to about a mile north of the US-11 overpass in Fort Payne.

Read More “I-59 Southbound Reconstruction and Rehabilitation from Georgia to Fort Payne”