Uprights for the overhead sign structures that will support the message boards on I-565 westbound between County Line Road and Greenbrier Road.

Updated timeline: I-565 overhead message board schedule changes

Motorists will soon benefit from travel information displayed on overhead message boards on I-565 in Limestone and Madison counties.

A contractor will install the dynamic message signs (DMS) at three locations as part of the ongoing $5.2 million advanced corridor management project. The project, which began in…

Read More “Overhead message boards coming to I-565”

Work continues on the interchange bridges over I-565 at Town Madison

Expect some travel delays overnight on I-565 westbound near the Town Madison Interchange (Exit 10) in Madison County.

Weather permitting, contractors will install striping and transition travel lanes to their final positions. Lanes were previously shifted to accommodate construction of the westbound off- and on-ramps and flyover bridges.

The work will take place from 7…

Read More “Lane closures set for tonight at I-565 Town Madison Interchange”

Signs for the project are in place, including this work zone sign near Exit 7 (County Line Road), at the west end of the project on the eastbound roadway.

The contractor on the I-565 widening project anticipates starting work next week to expand the interstate spur to six lanes through Madison.

The $29 million project stretches from west of County Line Road to east of Wall Triana Highway. It includes adding a third lane on each roadway and widening two sets of bridges —…

Read More “I-565 widening project in Madison to start”

Bridge girders are moved into place by cranes during the late night and early morning hours, when traffic volume on I-565 is the lowest.

The next series of bridge girders for the Town Madison Interchange on I-565 will be installed on multiple nights during the next three weeks.

Contractors will install the final girders for the westbound off-ramp and begin setting girders on the west-bound on-ramp.

The eastbound roadway will be closed for the safety of the public while…

Read More “Nighttime I-565 Exit 10 detours to continue”

Cranes are used to raise and position the massive steel girders that will support the future bridge deck of the westbound off-ramp at I-565 Exit 10.

The next series of bridge girders for the Town Madison Interchange on I-565 will be installed on several nights next week.   

The westbound roadway will be closed for the safety of the public while the girders — massive steel beams to support the future bridge decks of the Exit 10 westbound on- and off-ramps…