Work will soon begin on a $6.7 million project to paint and repair the US-431 bridges over the Tennessee River in Guntersville.

Painting of the Veterans Memorial Bridges on US-431 over the Tennessee River in Guntersville may begin next week.

ALDOT’s contractor, Cekra Inc., will paint the structural steel and rails of both half-mile long bridges. The faded green will be coated with battleship gray. The $6.7 million project will also include repairs to joints on the…

Read More “US-431 bridges in Guntersville to get paintjob”

ALDOT will implement a road diet during an upcoming resurfacing project, reducing the number of through lanes on SR-168 but adding a center turn lane.

A segment of SR-168 in Boaz will get a new look this spring after going on a diet — a road diet.

ALDOT will implement the road diet as part of a $1 million resurfacing project on SR-168 from US-431 to Darnell Street.

The contractor, Vulcan Materials, anticipates beginning work on the evening of…

Read More “Resurfacing, road diet ahead for SR-168 in Boaz”

Work will begin Thursday to install new signal poles and other signal upgrades at SR-69 and Sunset Drive in Guntersville.

Work to install new signal upgrades at SR-69 and Sunset Drive in Guntersville will begin Thursday, Feb. 19, weather permitting.

The work will take just a few days. ALDOT anticipates little impact on traffic.

The planned signal upgrades include new poles, mast arms, signal heads, pedestrian
heads, detection devices and signal retiming.

The signal upgrades are…

Read More “Signal upgrades at SR-69 and Sunset Drive to begin”

ALDOT workers make salt brine for pretreatment of state routes at the Dutton District Office in Jackson County on Friday.

ALDOT pretreated most state routes in North Alabama in the lead up to this weekend’s anticipated winters storm.

The pretreatment coverage, by county, in ALDOT’s North Region follows:

Colbert/Lauderdale/Franklin/Lawrence/Limestone/Morgan — all lanes and bridges of all state routes Madison — At least one lane in each direction on all routes and bridges and all lanes…Read More “Most North Alabama state routes pretreated ahead of winter storm”

ALDOT opened bids today for a project to paint and repair the Veterans Memorial Bridges on US-431 over the Tennessee River in Guntersville.

Of 11 bidders, contractor Cekra Inc. submitted the apparent low bid of $6,692,309. ALDOT anticipated bids between $11.9 and $14.5 million.

Construction is pending bid review and award of the contract. The…

Read More “Bids opened for painting, repair of US-431 bridges in Guntersville”

Venture Construction, a subcontractor for Vulcan Materials on the $6.8 million project, is applying a high friction surface treatment to parts of the highway through Lucas Gap, south of Cathedral Caverns Road.

Work began today to add a finishing touch to the resurfacing of US-431 north of Guntersville in Marshall County.

Venture Construction, a subcontractor for Vulcan Materials on the $6.8 million project, is applying a high friction surface treatment to parts of the highway through Lucas Gap, south of Cathedral Caverns Highway.

High friction surface treatments…

Read More “High friction surface treatment work begins on US-431”

Vulcan Materials will resurface about seven miles of US-431 from the north the Tennessee River in Guntersville to Cathedral Caverns Highway, south of Grant.

Contractors will soon begin two resurfacing projects near Guntersville in Marshall County.

Weather permitting, Vulcan Materials will start Monday, May 12, resurfacing about seven miles of US-431. The project extends from the north end of the Veterans Memorial Bridge over the Tennessee River in Guntersville to Cathedral Caverns Highway, south of Grant. The $6.8 million…

Read More “Two Marshall County resurfacing projects to start soon”

Workers fasten a center section of bridge girder. The old bridge, constructed in 1942, is in the background.

Cranes hoisted the final girder for the new SR-75 bridge at Lakeview into place Monday morning.

The girders – huge steel beams – will support the future bridge deck spanning Town Creek in DeKalb County, east of the Marshall County line.

The final girder was raised into place Monday morning. Bigger and better

The $13.7…

Read More “Girders installed for the new SR-75 bridge”