The I-65 Tennessee River Bridges underwent cleaning, painting, and various steel and concrete repairs since the rehabilitation project began in early 2024. Next week, the contractor will remove the traffic shifts that have been in place for most of the project's duration.

Travel lanes will soon return to their normal configuration on the I-65 Tennessee River Bridges.

The lanes on both bridges were shifted about two years ago to provide work areas for a $23.7 million bridge rehabilitation project.

The contractor, Cekra Inc., performed repairs to extend the useful lifespans of the 53-year-old bridges. The project included…

Read More “Lanes to return to normal on I-65 Tennessee River Bridges”

Work will soon begin on a $6.7 million project to paint and repair the US-431 bridges over the Tennessee River in Guntersville.

Painting of the Veterans Memorial Bridges on US-431 over the Tennessee River in Guntersville may begin next week.

ALDOT’s contractor, Cekra Inc., will paint the structural steel and rails of both half-mile long bridges. The faded green will be coated with battleship gray. The $6.7 million project will also include repairs to joints on the…

Read More “US-431 bridges in Guntersville to get paintjob”

Workers prepare an area of the northbound I-65 bridge deck for repair.

The contractor on the I-65 Tennessee River Bridge rehabilitation project made significant progress during around-the-clock lane closures the last two weekends. Cekra completed concrete repairs to the northbound bridge deck far ahead of schedule.

More around-the-clock lane closures, originally planned for the remaining two weekends in October, won’t be necessary.

No more daytime lane closures…Read More “I-65 bridge weekend lane closures canceled; deck repairs completed early”

To rehabilitate the Tennessee River Bridges, the contractor, Cekra, first rigged scaffolding to access work areas.

Motorists should expect single-lane closures for rehabilitation work on the northbound I-65 Tennessee River Bridge each weekend in October, beginning this Friday.

The contractor will close the outside lane about 6 p.m. on Fridays and reopen it about 5 a.m. on Mondays.

Please expect delays on the northbound roadway during the weekends. Plan additional…

Read More “Weekend lane closures planned for I-65N at Tennessee River Bridge”