Resurfacing, traffic stripe, guardrail, guardrail end anchors, and 2-foot safety widening on SR-38/US-280 from the Shelby County line (MP 31.859) to CR-25 (MP 37.455)
Region/County | East Central/Talladega |
Route | SR-38/US-280 |
Projected Start | April 28, 2023 |
Projected Completion | Spring 2024 |
Project Number | NH-HSIP 0038 551 100075184 |
Project Cost | $6,263,293.01 |
Funding Source | $5,035,687.58 in federal funds, $1,227,605.43 in state funds |
Project Status | Active |